Pre Outage Inspection
-
Pre-Outage Inspections are to capture the existing condition of the electrical system. During the inspection we need to check that the existing cabling, circuit breaker, control wiring and field outlets are fit for purpose and meet the current Australian standards. Items to consider are earth size, cable size is suited to the CB, core Identification.
Pre-Outage Sub-Circuit Inspection No.
-
Pre-Outage CB No.
-
Pre-Outage Circuit Description
-
Pre-Outage CB Current Rating
-
Circuit Cable Size
-
Circuit Phase allocation
-
Test Rotation at Field Outlet Pre Outage
-
Post Re- Energization Confirm the Field Outlet Phase Rotation is same as the Pre Outage
-
Test Rotation at Field Outlet
-
Post Re- Energization Confirm the Field Outlet Phase Rotation is same as the Pre Outage
-
Control wiring associated with circuit.
-
Capture existing wiring (photo, draw single line)