Title Page

  • Contract Name and Numbers

  • Description of Works

  • Subcontractor

  • Area Inspected (Please state building/level/room/zone/elevation/gridlines as per attached drawing)

  • Construction Drawing Ref

  • Other References (Inspection and Test Plan/Specification/Manufacturer's Technical Guide)

  • Supporting Documentation (Photographs/Marked-Up Drawings/Surveys/Test Records)

Untitled Page

  • Materials of type specified/approved (Checked by Sub-Contractor)

  • Materials of type specified/approved (Checked by Ventry)

  • Manufacturer's installation instructions obtained and method of installation will be in accordance with manufacturer's details (Checked by Sub-Contractor)

  • Manufacturer's installation instructions obtained and method of installation will be in accordance with manufacturer's details (Checked by Ventry)

  • Substrate surface prepared in accordance with manufacturer's details (Checked by Sub-Contractor)

  • Substrate surface prepared in accordance with manufacturer's details (Checked by Ventry)

  • Water levels established and any necessary precautions taken (Checked by Sub-Contractor)

  • Water levels established and any necessary precautions taken (Checked by Ventry)

  • Surfaces kept dry until relevant work completed (Checked by Sub-Contractor)

  • Surfaces kept dry until relevant work completed (Checked by Ventry)

  • Concrete/screed surfaces clean, smooth, and free from cavities and protrusions (Checked by Sub-Contractor)

  • Concrete/screed surfaced clean, smooth, and free from cavities and protrusions (Checked by Ventry)

  • Brickwork/blockwork surface as even as possible, and flush pointed or rendered (as specified) (Checked by Sub-Contractor)

  • Brickwork/blockwork surface as even as possible, and flush pointed or rendered (as specified) (Checked by Ventry)

  • Adequate ventilation maintained in confined spaces (Checked by Sub-Contractor)

  • Adequate ventilation maintained in confined spaces (Checked by Ventry)

  • Membrane applied in accordance with manufacturer's details etc. (Checked by Sub-Contractor)

  • Membrane applied in accordance with manufacturer's details etc. (Checked by Ventry)

  • Lap joints are pressed horizontal (Checked by Sub-Contractor)

  • Lap joints are pressed horizontal (Checked by Ventry)

  • Temperature is 5 deg C or above for laying membrane (Checked by Sub-Contractor)

  • Temperature is 5 deg C or above for laying membrane (Checked by Ventry)

  • Joints allowed to set/cure as recommended by manufacturer (Checked by Sub-Contractor)

  • Joints allowed to set/cure as recommended by manufacturer (Checked by Ventry)

  • Membrane to be protected from the follow on trades (Checked by Sub-Contractor)

  • Membrane to be protected from the follow on trades (Checked by Ventry)

  • Materials to be stored in dry conditions, temperature at 5 deg C or above and duly protected (Checked by Sub-Contractor)

  • Materials to be sorted in dry conditions, temperature at 5 deg C or above and duly protected (Checked by Ventry)

  • Rolls stacked on ends or as recommended by manufacturer (Checked by Sub-Contractor)

  • Rolls stacked on ends or as recommended by manufacturer (Checked by Ventry)

Comments

  • Any Comments

Final Inspection - All Items Completed and Inspection Passed

  • Inspected By:

  • Inspected By:

  • Inspected By:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.