Title Page
-
Contract Name and Numbers
-
Description of Works
-
Subcontractor
-
Area Inspected (Please state building/level/room/zone/elevation/gridlines as per attached drawing)
-
Construction Drawing Ref
-
Other References (Inspection and Test Plan/Specification/Manufacturer's Technical Guide)
-
Supporting Documentation (Photographs/Marked-Up Drawings/Surveys/Test Records)
Untitled Page
-
Ensure Subcontractor is an approved applicator of the system (Checked by Sub-Contractor)
-
Ensure Subcontractor is an approved applicator of the system (Checked by Ventry)
-
Risk assessment and method statement agreed (Checked by Sub-Contractor)
-
Risk assessment and method statement agreed (Checked by Ventry)
-
Manufacturer's literature and instructions obtained (Checked by Sub-Contractor)
-
Manufacturer's literature and instructions obtained (Checked by Ventry)
-
Spray system compatible with steelwork primer (Checked by Sub-Contractor)
-
Spray system compatible with steelwork primer (Checked by Ventry)
-
Specified system requires temporary protection against rain/frost etc. (Checked by Sub-Contractor)
-
Specified system requires temporary protection against rain/frost etc. (Checked by Ventry)
-
Compliance with COSHH assessment (Checked by Sub-Contractor)
-
Compliance with COSHH assessment (Checked by Ventry)
-
Work area and adjacent areas suitably protected and with satisfactory access (Checked by Sub-Contractor)
-
Work area and adjacent areas suitably protected and with satisfactory access (Checked by Ventry)
-
Surfaces clean and dry and free loose scale, rust, oil, grease (Checked by Sub-Contractor)
-
Surfaces clean and dry and free loose scale, rust, oil, grease (Checked by Ventry)
-
Air temperature more than 4oC (or as specified by manufacturer) (Checked by Sub-Contractor)
-
Air temperature more than 4oC (or as specified by manufacturer) (Checked by Ventry)
-
Humidity in accordance with manufacturer's recommendations (Checked by Sub-Contractor)
-
Humidity in accordance with manufacturer's recommendations (Checked by Ventry)
-
Application of bonding coat, if required (Checked by Sub-Contractor)
-
Application of bonding coat, if required (Checked by Ventry)
-
Check coating thickness for each area and applicator (Checked by Sub-Contractor0
-
Check coating thickness for each area and applicator (Checked by Ventry)
-
Protected from weather as specified by manufacturer (Checked by Sub-Contractor)
-
Protected from weather as specified by manufacturer (Checked by Ventry)
Comments
-
Any Comments
Final Inspection - All Items Completed and Inspection Passed
-
Inspected By:
-
Inspected By:
-
Inspected By: