Title Page

  • Contract Name and Numbers

  • Description of Works

  • Subcontractor

  • Area Inspected (Please state building/level/room/zone/elevation/gridlines as per attached drawing)

  • Construction Drawing Ref

  • Other References (Inspection and Test Plan/Specification/Manufacturer's Technical Guide)

  • Supporting Documentation (Photographs/Marked-Up Drawings/Surveys/Test Records)

Untitled Page

1st Fix Installation

  • Setting out with respect to gridlines/datum (Checked by Sub-Contractor)

  • Setting out with respect to gridlines/datum (Checked by Ventry)

  • Metal framing (Checked by Sub-Contractor)

  • Metal framing (Checked by Ventry)

  • Setting out of critical dimensions checked (Checked by Sub-Contractor)

  • Setting out of critical dimensions checked (Checked by Ventry)

  • Main batten/stud centres and studs correctly aligned (Checked by Sub-Contractor)

  • Main batten/stud centres and studs correctly aligned (Checked by Ventry)

  • Insulation installed correctly (Checked by Sub-Contractor)

  • Insulation installed correctly (Checked by Ventry)

  • Service within ceiling void fully completed before closing (Checked by Sub-Contractor)

  • Service within ceiling void fully completed before closing (Checked by Ventry)

Hold Point Inspection

  • Items above to be checked before work continues with photographic evidence recorded

2nd Fix Installation

  • Board installation/ceiling closure (Checked by Sub-Contractor)

  • Board installation/ceiling closure (Checked by Ventry)

  • Access panels/tiles provided at specified locations (Checked by Sub-Contractor)

  • Access panels/tiles provided at specified locations (Checked by Ventry)

  • Tape and jointing/rubbing down (Checked by Sub-Contractor)

  • Tape and jointing/rubbing down (Checked by Ventry)

  • Finished ceiling is free of damage (pre snagging) (Checked by Sub-Contractor)

  • Finished ceiling is free of damage (pre snagging) (Checked by Ventry)

  • Area left clean and tidy (Checked by Sub-Contractor)

  • Area left clean and tidy (Checked by Ventry)

Comments

  • Any Comments

Final Inspection - All Items Completed and Inspection Passed

  • Inspected By:

  • Inspected By:

  • Inspected By:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.