Information

  • Client

  • Job no.

  • Site Address

  • Conducted on

  • Prepared by

  • Personnel

Brick Inspection

  • Is brick inspection conducted for dwelling?

  • Note: For single dwellings complete Ground Floor internal/external only.

General

  • 1.01 Is site fencing intact? (No Damage)

  • 1.02 Is gate locked?

  • 1.03 All rubbish in designated area?

  • 1.04 Has all left over material been stacked neatly?

  • 1.05 Are boundary fences free of mortar splash?

  • 1.06 Have all leftover bricks and clutter been removed from scaffold?

Ground Floor External

  • 2.01 Is all brickwork complete?

  • 2.02 Are all sills adequately complete to windows and sliding doors?

  • 2.03 Has hot water system box been tied into brickwork?

  • 2.04 Is all brickwork less than 15mm overhang off concrete slab rebate?

  • 2.05 Are all weep holes free from mortar?

  • 2.06 Are base bed joints less than 20mm in thickness?

  • 2.07 Is all brickwork plumb and straight? (refer to Guide to Standards and Tolerances)

  • 2.08 Are all joints and perps of uniform thickness?

  • 2.08.1 Are perps to internal corners uniform and plumb?

  • 2.08.2 Have expansion joints been installed with 10mm expansion foam, adequate expansion ties and are free from mortar?

  • 2.09 Has all hoop irons been installed?

  • 2.10 Are all rubber seals covering gaps between window and brick sills?

  • 2.11 Are ALL bricks laid level? (Any crooked brickwork should be photographed and noted)

  • 2.12 Have all profile holes been filled and pointed?

  • 2.13.2 Vertical alignment: Are all perpends within 15mm vertical alignment for every 2m of height in wall?

  • 2.14 Is brickwork free of excessive chips?

  • 2.15 Are all mortar joints uniformly finished?

  • 2.16 Is mortar colour and texture consistent?

  • 2.17 Have all lead flashings been installed correctly?(applicable to single storey only)

  • 2.08.2 Have expansion joints been installed with 10mm expansion foam, adequate expansion ties and are free from mortar?

Ground Floor Internal

  • 2.01 Are glass panels free of scratches?

  • 2.02 Are aluminum frames free of scratches/dents?

  • 2.03 Are sliding door tracks free of scratches dents?

  • 2.04 Are all cavities and noggins clean and free of mortar droppings?

  • 2.05 Are windows and doors free of mortar splash?

  • 2.06 Have adequate ties been installed?

  • 2.07 Are all cavities within the minimum 25mm tolerance?

  • 2.08 Have all lead flashings been installed correctly?(applicable to single storey only)

  • 2.09 Has slab been swept and any bracing timber been stacked neatly?

Two Storey

  • Two Storey Dwelling (please tick)

First Floor External

  • 2.01 Is all brickwork complete?

  • 2.02 Are all sills adequately complete to windows and sliding doors?

  • 2.03 Have all Parapet walls been finished with a header course?

  • 2.05 Are all weep holes free from mortar?

  • 2.06 Is all brickwork plumb and straight?

  • 2.07 Are all joints and perps of uniform thickness?

  • 2.08.1 Are perps to internal corners uniform and plumb?

  • 2.08.2 Have expansion joints been installed with 10mm expansion foam, adequate expansion ties and are free from mortar?

  • 2.08 Are all rubber seals covering gaps between window and brick sills?

  • 2.09 Are ALL bricks laid level? (Any crooked brickwork should be photographed and noted)

  • 2.10 Have all profile holes been pointed?

  • 2.13.2 Vertical alignment: Are all perpends within 15mm vertical alignment for every 2m of height in wall?

  • 2.11 Are perps to internal corners uniform and plumb?

  • 2.12 Is brickwork free of excessive chips?

  • 2.13 Is all mortar joints uniformly finished?

  • 2.17 Have all lead flashings been installed correctly?

First floor internal

  • 2.01 Are glass panels free of scratches?

  • 2.02 Are aluminum frames free of scratches/dents?

  • 2.03 Are sliding door tracks to balconies free of scratches dents?

  • 2.04 Are all cavities and noggins clean and free of mortar droppings?

  • 2.05 Are windows and doors free of mortar splash?

  • 2.06 Have adequate ties been installed?

  • 2.07 Are all cavities within the minimum 25mm tolerance?

  • 2.08 Have all lead flashings been installed correctly?

  • 2.09 Has Flooring been swept and bracing timbers stacked neatly?

Comments

  • 2.20 In your opinion, has work been completed in a clean and proficient manner?

  • 2.21 Can this job be paid without retention?(if unsure contact Construction Manager)

  • Please add any additional information/comments

  • Site Manager Sign off

Please note: This is an internal Quality Control document conducted visually, this report does not indemnify bricklayer from any errors that may be identified in the future

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.