Information
-
Site Address
-
Job No.
-
Conducted on
-
Prepared by
General
-
1.01 Is site fencing intact? (No Damage)
-
1.02 Was gate locked?
-
1.03 All rubbish in designated area?
-
1.04 Has ground and first floor been swept?
-
1.05 Has all left over material been stacked neatly?
-
1.06 Has leftover material been picked up for recycling?
Gyprock Inspection
Note: Use hard lead pencil to mark all areas of concern
-
2.01 Have you checked all setting Joints?
-
2.02 Are all joint compounds free from tool marks and ridges?
-
2.03 Are all internal and external corners free from pin holes?
-
2.04 Are External angles adjacent to kitchen cupboards plumb, including bulkhead? (Note: plaster cornices are defective if they deviate from a straight line greater than 4mm over a length of up to 2m)
-
2.05 Have you checked extent of tiling in wet areas?(Note: if tiling to ceiling, cornice to be installed after tiling)
-
2.06 In your opinion, has work been completed in a clean and proficient manner?
-
2.07 Can this Job be paid?
-
2.08 General Comments
-
Site Manager Sign off