Information
-
Site Address
-
Job No.
-
Conducted on
-
Prepared by
General
-
1.01 Is site fencing intact? (No Damage)
-
1.02 Was gate locked?
-
1.03 All rubbish in designated area?
-
1.04 Has ground and first floor been swept?
-
1.05 Has all left over material been stacked neatly?
Fixer Inspection
-
2.01 Have all Mitres to architraves been sanded and made good?
-
2.02 Have all Mitres to skirting been sanded and made good?
-
2.03 Are all joints to skirtings aligned and flush? (note: Butt Joints are not accepted)
-
2.04 Have Jambs and doors been installed to match prospective floor finishes?
-
2.05 Do all doors have an even gap around? (note: no less than 4mm required and no more than 5mm)
-
2.06 Is Clearance adequate from bottom of door to finish floor surface? (note: no greater than 20mm tolerance)
-
2.07 Are all doors free from distortion? (note: bending in door heights between 2040 and 2400 high- greater than 6mm is deemed defective)
-
2.08 Have all external doors been sealed at the bottom, i.e. front entry, laundry and garage?
-
2.09 Do all doors operate free from binding onto jamb? (note: including aluminum French doors to balconies)
-
2.10 Have all windows been finished true and plumb?
-
2.11 Do all windows operate freely?
-
2.12 Have all nails been adequately punched to all window and door reveals?
-
2.13 Have all sliding door sashes been installed and adjusted?
-
2.14 Do all cavity sliding doors operate freely and plastic guide adjusted correctly?
-
2.15 Has carpet band been installed to all void areas?
-
2.16 Has all beading in garage been installed correctly?
-
2.17 Was all material present for fixer to complete?
-
2.18 In your opinion, has work been completed in a clean and proficient manner?
Comments
-
Can this Job be paid?
-
Site Manager sign off