Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Last Inspection conducted
-
Prepared by
-
Location
-
Inspection party
- Peter Tsoukalas, Senior Asset Planner Dams headworks
- Stewart Dahms, Acting Asset Plann Dams Headworks
- Eric Pepe, C&M Millbrook
- Alex Przygoda, C&M Millbrook
- Andrew Johanning, C&M Port Pirie
- Neil Mclean, Snr Construction and Mtce Wkr
- Mark Williams,Snr Construction and Mtce Wkr
- Peter Pavy, Mgr Land Mgmt & Reservoirs
- Dylan RIbbons, Acting Asset Plann Dams Headworks
Add member
-
Name
-
Position
-
Company
Operational Status at time of inspection
-
Dam Details
-
Consequence Category
-
Storage Level Gauge board (m), FSL=18.7
-
Storage Level mAHD, FSL = 295.01
-
Water in Storage ML, capacity at FSL = 6,370
-
release via spillway
-
Other Comments
-
Photos
-
Sketch
Conditions at time of inspection
-
Weather
-
Estimated Max Temperature degrees celsius
-
Sky
-
Wind
-
Rain
-
Days since last rain
-
Other Comments
-
Photos
-
Sketch
Dam Safety Management
-
O&M Manual on Site
-
O&M Manual Reviewed
-
Dam Safety Emergency Plan on Site
-
Dam Safety Emergency Plan reviewed
-
Drawings on site
-
Operator Knowledge
-
Operator training
-
Other Comments
-
Photos
-
Sketches
Crest
-
Cracks
-
Vegetation
-
Sink Holes
-
Subsidence
-
Overtopping
-
Wheel ruts
-
Other observations
-
Take photos of any deficiencies found on crest
-
Sketch
Downstream Face
-
Cracks
-
Slips
-
Erosion
-
Vegetation
-
Animal Activity
-
Bulges
-
Subsidence
-
Seepage
-
Other deficiencies/comments for the downstream face
-
Photos
-
Sketch
Upstream Face
-
Cracks
-
Slips
-
Erosion
-
Vegetation
-
Subsidence
-
Animal Activity
-
Bulges
-
Wave Effects
-
Rock Facing
-
Take photos of any deficiencies found on upstream face
-
Other deficiencies/comments for the upstream face
Abutments
-
Cracks
-
Slips
-
Erosion
-
Vegetation
-
Subsidence
-
Seepage
-
Take any photos of abutment observations
-
Other deficiencies/comments for abutments
Area Downstream of Dam
-
Seepage
-
Subsidence
-
Bulges
-
French Drain
-
Comments
-
Photos
-
Sketch
Spillway
-
Concrete ribbon wall
-
Upstream approach
-
Downstream channel
-
Vegetation
-
Erosion
-
Other comments
-
Photos
-
Sketch
Outlet tunnel
-
Concrete lining
-
Leakage
-
Pipework
-
Tunnel portal
-
Outlet cutting
-
Scour
-
Outfall
-
Security
-
Other comments
-
Photos
-
Sketch
Outlet Tower
-
Internal walls
-
Leakage
-
Pipework
-
Valves
-
Inlet screens
Internal access
-
Platform 1 (Bottom)
-
Platform 2 (Middle)
-
Platform 3 (Top)
-
Roof platform
-
Other Internal access
-
Security
-
Superstructure
-
Crane
-
Other comments
-
Photos
-
Sketch
Outlet Works Operation
-
Valve Schematic
-
Top valve BU1 (EL287.95 mAHD) status
-
Top Valve BU1 (EL287.95 mAHD) tested
-
Top Valve BU1 (EL287.95 mAHD) last tested
-
Top Valve BU1 (EL287.95 mAHD) test satisfactory
-
Other comments
-
Photos
-
Lower valve BU2 (EL281.98 mAHD) status
-
Lower valve BU2 (EL281.98 mAHD) tested
-
Lower valve BU2 (EL281.98 mAHD) last tested
-
Lower valve BU2 (EL281.98 mAHD) test satisfactory
-
Other comments
-
Photos
-
Double Gate Valve BU3 (EL276.46 mAHD) status
-
Double Gate Valve BU3 (EL276.46 mAHD) tested
-
Double Gate Valve BU3 (EL276.46 mAHD) last tested
-
Double Gate Valve BU3 (EL276.46 mAHD) test satisfactory
-
Other comments
-
Photos
-
Bundaleer trunk main guard valve (BU4) status
-
Bundaleer trunk main guard valve (BU4) tested
-
Bundaleer trunk main guard valve (BU4) last tested
-
Bundaleer trunk main guard valve (BU4) test satisfactory
-
Other comments
-
Photos
-
Scour valve BU5 status
-
Scour valve BU5 tested
-
Scour valve BU5 last tested
-
Scour valve BU5 test satisfactory
-
Comments
-
Photos
-
Pressure relief isolating valve BU6 status
-
Pressure relief isolating valve BU6 tested
-
Pressure relief isolating valve BU6 last tested
-
Pressure relief isolating valve BU6 test satisfactory
-
Comments
-
Photos
-
Overall comments
-
Overall photos
Inlet Works
Bundaleer Weir
-
Crest
-
Downstream face
-
Upstream face
-
Abutment blocks
-
Area downstream
-
Outlet gates
-
Outlet screen
-
Scour valve
-
Bundaleer channel
-
Bundaleer aqueduct
-
Comments
-
Photos
Freshwater creek Weir
-
Crest
-
Downstream face
-
Upstream face
-
Abutment blocks
-
Outlet works
-
Channel
-
Comments
-
Photos
Broughton Weir
-
Crest
-
Downstream face
-
Upstream face
-
Abutment blocks
-
Outlet works
-
Channel
-
Scour Valve
-
Comments
-
Photos
-
Other comments
-
Photos
-
Sketch
Access to Dam
-
Right Abutment
-
Left abutment
-
Other access to dam notes
-
Sketch
-
Access to dam photos
Reservoir
-
Landslips around rim
-
Boat Ramp
-
Other comments
-
Sketch
-
Photos
Communications
-
Telemetry
-
Telephones
-
Radios
-
Other comments
-
Sketch
-
Photos
Power Supply
-
Normal
-
Standby
-
Other comments
-
Sketch
-
Photos
Instrumentation
-
Pnuematic piezometers
-
Vibrating Wire piezos
-
Standpipes
-
Survey System
-
Seepage collection
-
Other comments
-
Photos
-
Sketch
Surveillance
-
Consequence Category
-
Rainfall
-
Rainfall observation frequency meets ANCOLD guidelines
-
Storage Level
-
Storage Level Observation frequency meets ANCOLD guidelines
-
Seepage
-
Seepage Observation frequency meets ANCOLD guidelines
-
Seepage Analysis
-
Seepage Analysis observation frequency meets ANCOLD guidelines
-
Pore Water Pressure
-
Pore water pressure observation frequency meets ANCOLD guidelines
-
Surface Displacement
-
Surface Displacement observation frequency meets ANCOLD guidelines
-
Internal displacement
-
Internal displacement observation frequency meets ANCOLD guidelines
-
Seismological
-
Seismological observation frequency meets ANCOLD guidelines
-
Telemetry
-
Telemetry observation frequency meets ANCOLD guidelines
-
Visual Inspections
-
Visual Inspection observation frequency meets ANCOLD guidelines
-
Other comments