Information

  • Employee Name - (JHA) - Name of Project (Written just like this):

  • Document No.

  • Conducted on

  • Prepared by:

  • Location
  • Personnel (All persons working today):

Project site information

  • Project name:

  • Task activity:

  • Date:

  • Work being performed for:

Check applicable anticipated or potential hazards

  • Demolition:

  • Underground tank removal/disposable/high vapors:

  • Activities in or near traffic areas:

  • Concrete cutting or coring:

  • Mobile heavy equipment activity (excavators, dump trucks, vacuum and hydovac trucks):

  • Pile driving / shoring:

  • Work affecting integrity of critical controls:

  • Welding, cutting, grinding:

  • Hydoblasting / sand blasting:

  • Trenching (Mechanical or by hand):

  • Clearing:

  • Rigging:

  • Airborne contaminants:

  • Other (specify) :

Critical procedures: where work involves any of the following hazards must be incorporated into JHA

  • Work at heights above 6ft:

  • Confined space entry (includes tank cleaning):

  • Electrical or mechanical lockout (live, isolation, lock out / tag out:

  • Heavy equipment lifting (cranes, boom trucks, excavators):

  • Drilling borehole / excavations (Sub-surface clearance, locates):

  • Entry into excavations/Trenches (4ft) deep:

  • Hot work (in potentially explosive atmosphere):

Ensure all hazards identified are addressed in JHA below

  • Hazard 1: Sequence of job, Steps in order, breaking job into manageable pieces:

  • Potential hazards. (Ex. underground services, hazard zone etc.):

  • Safety controls to reduce or eliminate hazard:

  • Hazard 2: Sequence of job, Steps in order, breaking job into manageable pieces:

  • Potential hazards. (Ex. underground services, hazard zone etc.)

  • Safety controls to reduce or eliminate hazard:

  • Hazard 3: Sequence of job, Steps in order, breaking job into manageable pieces:

  • Potential hazards. (Ex. underground services, hazard zone etc.):

  • Safety controls to reduce or eliminate hazard:

  • Hazard 4: Sequence of job, Steps in order, breaking job into manageable pieces:

  • Potential hazards. (Ex. underground services, hazard zone etc.):

  • Safety controls to reduce or eliminate hazard:

  • Hazard 5: Sequence of job, Steps in order, breaking job into manageable pieces:

  • Potential hazards. (Ex. underground services, hazard zone etc.):

  • Safety controls to reduce or eliminate hazard:

Tools / Equipment ( list of tools and equipment and their storage on site, if relevant to safety

  • List

Required PPE ( minimum requirement: hard hat, spoggles, gloves, hearing band, type 2 vest).

  • Eye protection:

  • Hearing protection:

  • Fall protection:

  • Hand protection:

  • Head protection:

  • Type 2 or 3 reflective vest (Required when working near a roadway or moving vehicles and equipment):

  • Foot protection:

  • Portable gas monitor:

  • Airborne particulate monitor:

  • Other (fire retardant coveralls, breathing apparatus, etc) specify :

Outside authorities:

  • Outside authorities

Disposal of designated substances, surplus, or impacted materials (disposal details, e.g when, where, how?)

  • Add signature

Inspector & Support

  • Prepared by

  • Date

  • Person carrying out work

  • Date

  • Person carrying out work

  • Date

  • Person carrying out work

  • Date

Site Foreman:

  • JHA approved associate signature

  • Date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.