MyDeck Installation
-
Have products been stored in a dry and protected location?
-
Are fixings checked against the latest Rev fixing schedule?
-
Items such as the Jacuzzi been disconnected and moved prior to works commencing?
-
Has the roof been leak tested prior to works commencing?
-
Has the roof been cleared and free from screws or other possible items that can puncture the membrane?
-
Has the insulation and membrane been reinstalled?
-
HOLD POINT
-
Has the Boxrail and Cleat Substructure System been installed at the correct centres i.e. maximum of 1200mm cleats and 1000mm centres of rails?
-
Has a maximum overhand of 250mm from the cleat centre to the end of the supporting rail been maintained?
-
Has the supporting rails been cut so boards do not overhang by more than 200mm?
-
Are the rails inserted into the cleats at the correct height?
-
Are the rails level along their line as well as with adjacent cleats?
-
Using the grooves as a guide, are all fixings into the rails through the cleats installed on both sides and 30mm apart?
-
HOLD POINT
-
Have boards been installed using appropriate fixings?
-
Has a 6mm gap between maintained?
-
Has a minimum of 3mm and maximum of 8mm gap been allowed between each board for drainage?
-
Has the capping channel been installed?
-
Has the draining channels been positioned where dripping does not cause a nuisance? Installation of the draining channel been followed as per the manufacturers guidance?
Sign off
-
A2O Representative
-
Subcontractors Supervisor