Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

For Breakdown of task spec see links

  • https://pfpl-my.sharepoint.com/:f:/g/personal/barrywright_pfpleisure_org/ElAUOsS0tklOjTsG0rzTutsB-AdK7p33IMqvjwgEg5C1xw?e=iDxcj3

For electrical inspection checks see links

  • https://pfpl-my.sharepoint.com/:f:/g/personal/barrywright_pfpleisure_org/EvvKMfqgbm1LnSDZt9cwARQBxtPdldRnovsn-X4zBwWUIQ?e=bkmPm0

Area 1-Reception Area entrance Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes radiators,all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Emergency light numbers Outside 1 (M) internal 2,3 (M) Flick test at keyswitch in finance office in intake cupboard fed from DBQ/DBT1 CT 5/L1

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • reception sockets under counter/ back wall (DBQ) DBT1, CT1/L2, Socket for car registration machine ..... Double socket by auto doors

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with loose leads

  • Hair driers serviced if applicable to this area?

Area 2 Ops/DM Office-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Emergency light number 11 (M) Flick test on wall at switch Fed from DBQ/DBT1 CT 4/L1

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Ops/DM office sockets (DBQ) DBT1, CT1/L2

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with loose leads

  • Hair driers serviced if applicable to this area?

Area 3 Sales Office-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Emergency light number 12 (M) Flick test on wall at switch Fed from DBQ/DBT1 CT 4/L2

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Ops/DM office sockets (DBQ) DBT1, CT1/L2

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with loose leads

  • Hair driers serviced if applicable to this area?

Area 4 Admin/Finance Office-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Emergency light number 13,14 (M) Flick test on wall at switch Fed from DBQ/DBT1 CT 4/L2

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Admin office sockets DBQ/DBT1 CT 1/L1

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with loose leads

  • Hair driers serviced if applicable to this area?

Area 5 Creche-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Creche emergency number 4,5,6,7,8,9 M, 10 fire exit on outside N/M Flick test at keyswitch in finance office cupboard Fed from DBQ/DBT1 CT 4/L3

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Crech sockets DBQ/DBT1 CT 1/L3

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with loose leads

  • Hair driers serviced if applicable to this area?

Area 6 GM office-pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Creche emergency number 16a, test within room at keyswitch isolate at DBQ/DBT1 Circuit No 5L2

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 7 Vend seating/store/dryside corridor/playzone area including foyer outside GM office kitchen/Intake room-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Item Number 074 - Ground floor
    - Electric cupboard - Boarding
    to internal door header panel

    074.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Emergency Numbers 15,16 keyswitch in Finance Office Electric Cupboard/DBT1 Circuit No 5L2 ,17 keyswitch in Play zone Electric Cupboard/DBT6 Circuit No 1L2, 18 keyswitch in Play zone Electric Cupboard DBP/DBT6 Circuit No 1L3, 19 keyswitch in Play zone Electric Cupboard DBP/DBT6 Circuit No 1L1

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with loose leads replaced

  • Hair driers serviced if applicable to this area?

Area 8 Sports hall and stores/office-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of each items (29,60,61,62) current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Asbestos Item Number 029 (dryburgh hall small store right hand) - First floor -
    Small right hand store off public
    hall - Grey tile with bitumen to
    floor.

    IMG_8700.JPG
  • Asbestos Item Number 060 (dryburgh hall behind stage) - First floor -
    Corridor behind stage - Grey
    tile and bitumen to floor

    IMG_8707.JPG
  • Asbestos Item Number 061 (dryburgh hall large store) - First floor -
    Large store area - Grey tile and
    bitumen to floor beneath
    modern linoleum.

    IMG_8706.JPG
  • Asbestos Item Number 062 (dryburgh hall small electrical intake store left hand)- First floor -
    Small left hand store off public
    hall - Grey tile with bitumen to
    floor.

    IMG_8707.JPG

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 9 Male dryside change-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly including no works being carried out in these areas without prior management/discussion with client

  • Item Number 088 - Ground floor - Male changing sub-floor duct - Inaccessible - No access to internal aspects of service duct.
    Item Number 089 - Ground floor - Male changing sub-floor duct - Inaccessible - No access to internal aspects of service duct.

    8.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 10 Female dryside change-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly including no works being carried out in these areas without prior management/discussion with client

  • Item Number 071 - Ground floor
    - Female toilets sub-floor ducts
    - Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 072 - Ground floor
    - Female toilet sub-floor ducts -
    Inaccessible - No access to
    internal aspects of service
    ducts.

    071.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • FAT inspection completed if applicable to this area?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 11 Teaching pool changes x 4 and corridor Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 12 Teaching pool male toilet area-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 13 Teaching pool female toilet area-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 14 Teaching pool and store -Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly including no works being carried out in these areas without prior management/discussion with client

  • Item Number 067 - Ground floor
    - Main pool area sub-floor ducts
    - Inaccessible - No access to
    internal aspects of service
    ducts at deep end of the pool.
    Item Number 068 - Ground floor
    - Training pool area sub-floor
    ducts - Inaccessible - No
    access to internal aspects of
    service ducts.

    067.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 15 Teaching pool fire exit corridor and intake/stores x 3-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 16 Main pool area -Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly including no works being carried out in these areas without prior management/discussion with client

  • Asbestos Item Number 040 - Ground floor
    - Lift motor room -
    Inaccessible.

    IMG_8702.JPG

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 17 Health suite -Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 18 Corridor from main pool leading to teaching pool including first aid room and 2x store rooms-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Item Number 052 - Ground floor
    - First aid room cupboard -
    Boarding panels to boxwork to
    ceiling of cupboard.
    Item Number 053 - Ground floor
    - First aid room cupboard -
    Boarding panel to left wall of
    cupboard.

    052,053.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 19 Vilage change including corridor cleaning store group changes and 2x store rooms-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly including no works being carried out in these areas without prior management/discussion with client

  • Item Number 059 - Ground floor
    - Changing area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 060 - Ground floor
    - Changing area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 062 - Ground floor
    - Locker area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 063 - Ground floor
    - Locker area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 064 - Ground floor
    - Locker area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 065 - Ground floor
    - Locker area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.
    Item Number 066 - Ground floor
    - Locker area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.

    059,06.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 20 Village change male-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 21 Village change female-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly including no works being carried out in these areas without prior management/discussion with client

  • Item Number 061 - Ground floor
    - Changing area sub-floor duct -
    Inaccessible - No access to
    internal aspects of service
    ducts.

    061.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 22 Village change disabled-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 23 Squash corridor and courts throughout.-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 24 Treatment rooms x 2-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 25 Female toilet and foyer bottom of stairs leading to plantroom-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 26 Gym stairs and landing area to upper level including intake room-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 27 Main gym including consultation room/intake Intake cupboard,back fire exit and main gym back void room -Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 28 Main gym roof plant-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 29 Spin room and intake room-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly.

  • Asbestos Item Number 022 - Ground floor
    - Loft hatch above locker area -
    Inaccessible due to position of
    hatch.

    IMG_8699.JPG

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 30 Lola jones foyer and lift motor room-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place. for motor room this can be inspected monthly for lift/wheel room shaft complete either when insurance inspector on site or service company this is also for the annual by wcs

  • Item Number 001 - Ground floor
    - Lift motor room - Boarding
    panels to lift shaft wall.
    Item Number 006 - First floor -
    Lift shaft - Cement flue pipe to
    corner of lift shaft. Item Number 007 - Roof Void -
    Lift wheel room - Cement flue
    pipe adjacent to rear wall.
    Item Number 008 - Roof Void -
    Lift wheel room - Bitumen
    residue within redundant timber
    shuttering to reinforced
    concrete roof.

    001,006,007,008.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 31 Lola jones stairs leading to first floor landing and corridors-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Item Number 048 - First floor -
    Lift lobby - Boarding to 6 No
    panels between ceiling lights.

    048.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 32 Dance studio and cupboards-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 33 meeting room-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 34 Lola jones male toilet and intake cupboard-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 35 Lola jones female toilet-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed. This is to include sauna bench/heater protection frame security and condition and steam room tiling/steam Outlet protection frame.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Sauna/Steam along with fabric finishes either on night shift or via one morning prior to turning on have you completed full internal inspection on both inclusive of: Sauna heaters Condition no rubbish visible, temp stats on both secure with no visible damage, steam outlet secure and in correct position, signage in place, steam generator drum internally inspected and descaled as per manufacturers guidance

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 36 Lola jones foyer store-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Item Number 049 - First floor -
    Store room - Floor tile(s)
    themoplastic (beige) with
    bitumen adhesive.
    Item Number 050 - First floor -
    Store room - Floor tile(s)
    themoplastic (black) with
    bitumen adhesive.
    Item Number 076 - First floor -
    Store room cupboard - Floor
    tile(s) themoplastic (beige) with
    bitumen adhesive

    076.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 37 Lola jones hall/stage and cupboard/intake and store room-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 38 Lola jones kitchens/prep rooms x 2 -Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 39 Lola jones back corridors/fire exit route to lower exit and store/plantrooms x 3 -Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area (77,79,80) for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place. (item 78) presumed asbestos as no key so no works involving change to the structure ie building works until survey is completed

  • Item Number 077 - First floor -
    Plant room - Boarding to header panel over door. Item Number 078 - First floor -
    Landing store - Inaccessible -
    No access to internal aspects
    of store.
    Item Number 079 - First floor -
    Plant room - Boarding to header panel over door.
    Item Number 080 - First floor -
    Plant room - Boarding to
    cladding to steel beam at high
    level.

    079.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 40 corridor and stairs leading to plantroom-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 41 Poolside spectator seating and walkways-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Asbestos Item Number 007 - Ground floor
    - Kitchen area - Bitumen pad to
    underside of sink

    IMG_8696.JPG
  • Note One additional area of presumed Asbestos as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly.

  • Asbestos Item Number 015 - Ground floor
    - Pool equipment store -
    Bitumen damp proof course
    within wall

    IMG_8698.JPG

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 42 staffroom and treatment rooms and toilets including stairs and corridors-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Item Number 032 - First floor -
    Staff room - Floor tile(s)
    themoplastic with bitumen
    adhesive under red carpet.

    032.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 43 Back stair well upper and lower including foyer leading to lower plantroom-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly.

  • Asbestos Item Number 065 - First floor -
    Pool supply fan room -
    Inaccessible.

    IMG_8708.JPG

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 44-Lower plantroom-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Boundary Line-As per PFP Spec

  • Car Parks and Drives-As per PFP Spec

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.Not for forward planning on pool calorifier replacement.

  • Item Number 009 - Basement -
    Plant room - Gasket(s) to pool
    calorifier assembly (asset No
    23).
    Item Number 010 - Basement -
    Plant room - Gasket(s) to
    redundant flange assembly on
    floor in front of filter No 3.

    009,010.png
  • Elevations-As per PFP Spec

  • Landscaping, External contractor completed as per contract spec, any additional works needed or query's direct to CMA

  • Downpipes/Rain water goods-As per PFP Spec

  • Roofs-As per PFP Spec Mansafe used where applicable, Winter Months weekly visual

Area 45 Main plantroom throughout-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

  • View Asbestos located in this area for change compared to original survey (below in comments) and since last check, take a picture of areas current condition, if change has occurred please report this, make sure label identifying asbestos is in place.

  • Item Number 016 - First floor -
    Staff room - Floor tile(s)
    themoplastic with bitumen
    adhesive.
    Item Number 017 - First floor -
    Toilet - Floor tile(s)
    themoplastic with bitumen
    adhesive.
    Item Number 018 - First floor -
    Plant room 1 - Gasket(s) to
    steel flange joints front
    assembly to calorifiers 2.I
    item Number 019 - First floor - Plant room 1 - Gasket(s) to steel flange joints front assembly to calorifiers 1
    Item Number 023 - First floor - Plant/Tank room - Gasket(s) to steel flange joints adjacent to sports hall supply fan.
    Item Number 027 - Roof Void - Training pool roof void - Mastic to steel ducting joints

    016,017,018,019,023,027.png

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Room lighting inspection/Emergency Lighting inspection visual/flick test completed?

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 45-Internal/External Drainage

  • Has external contractor completed full internal/external drainage clean- April/Nov

Area 24-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Building fabric: Doors/Fire doors, Ceiling finishes openable windows, Glass/windows seals/fixings,internal wall finishes, floor finishes all Inspections associated to this area as per PFP spec.

  • Full Locker inspection completed

  • Full Cubical inspection completed

  • Sanitary Fittings-showers/buttons, toilet seats, Pans, pan flushing mechanism, sinks, taps, urinals, urinal flushing mechanism, all safe secure free from damage and in working order.

  • Vents/Grills/AC Filters cleaned If applicable to this area.

Monthly Electrical Checks-Emergency lighting and general lighting Monthly, FAT monthly, Fixed Wiring (switches,Sockets,Fixings) RCD’s and PAT items as per PFP guidance Quarterly. All new PAT items to be added to the online List of items. All remedials take picture evidence Make safe/repair where needed with items added to the site ‘Helpdesk’ log.

  • Electrical Fixed Wiring Inspections- Due and Inspection Complete? Jan/Apr/Jul/Oct

  • FAT inspection completed if applicable to this area?

  • PAT inspection completed if applicable to this area and month? Jan/Apr/Jul/Oct

  • RCD inspection completed-if due and applicable to this area? Jan/Apr/Jul/Oct

  • Hair drier replacement carried out this month if applicable to this area? June-Hair driers with cable leads replaced

  • Hair driers serviced if applicable to this area?

Area 44-External Areas Not Covered on other Checks-Pictures taken of ALL remedials, add these remedials to site 'Heldpdesk' or Forward Planning logs if no remedials but life cycle renewal project needed.

  • Boundary Line-As per PFP Spec

  • Car Parks and Drives-As per PFP Spec

  • Note No Asbestos located within this area, however it is presumed as when survey was completed no access was possible at the time of test If major works are required Asbestos survey will need completing prior to carrying out, however Each lift engineer on attendance needs to be informed of potential asbestos and report back if they are completing any works out of normal service works which could potentially disrupt/expose any asbestos that may be present. Tick yes that you are noting this and managing accordingly.

  • Asbestos Item Number 051 - External -
    Sub station - Inaccessible.

    IMG_8704.JPG
  • Elevations-As per PFP Spec

  • Landscaping, External contractor completed as per contract spec, any additional works needed or query's direct to CMA

  • Downpipes/Rain water goods-As per PFP Spec

  • Roofs-As per PFP Spec Mansafe used where applicable, Winter Months weekly visual

  • External lighting inspection/Emergency Lighting inspection visual/flick test completed?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.